P0Closed Cycle · Jan 6 – Mar 28, 2026
Closed chapter
Q1 2026 Security & Compliance Sprint
Sponsor Emma Novak (CTO) · Owner Devon Wu
Chapter completion100%
Cycle window
Jan 6 – Mar 28, 2026
Included problems
0 of 5 open
Goals
0
B
Included Problems
Frozen at lock. This is the exact set this cycle is committed to.
Rollup
Closed critical audit findings and stood up baseline SBOM coverage across services.
Included(0)
Locked scopeNo problems included.
C
Goals
The goals this cycle committed to. Frozen at lock.
This chapter had no goals recorded.
F
Progress Tracking
Final numbers at close.
Overall completion
100%
across all goals
Daily action progress
0 of 0
tasks completed
Monthly metric movement
Closed
See outcome below
Per-problem movement
G
Learning
What worked, what didn't.
What worked
- Critical audit findings 7 → 0
- SBOM coverage 12% → 94%
- Median vuln time-to-patch 41d → 9d
Outcome
3 of 4 problems resolved · 1 partially addressed